Results of 2009 Northwest Trail Alliance build days at L.L. Stub Stewart State Park...

New loop extension mostly done, plus started on south lower trail.  What is highlighted in green is what has been constructed so far.   There's more than 6 miles of single track planned.   see below for 2009 stats.

...what was done got done over 6 scheduled build days plus 3 adhoc prep days.

164 volunteer hours, 20 volunteers (25% came to more than one build day)... This represents about $3,000 in donated labor from Northwest Trail Alliance to Oregon Parks & Recreation Department.

Keith Shoenrock
Jason Van Horn

Aaron McBride
Stephen Street
Jacque LeFore
Dan Rawlinson
Jill Chickering
Jason Flint
Colin Maher
Mike Fischer
Robert Hildum
Brent Engstrom
David Csik
John Joy
Michael Patterson
Dan Owens
Kirby Mansberger
Alex Hyde
Brian Muck

 

you all rock!     See you next build season (or at an adhoc build day this winter...)